How to migrate all the projects to a new Wise Share Point? Is this documented somewhere?

Created: 04 Jan 2010 • Updated: 05 Jan 2010 • 2 comments
CableGuy41's picture
+12 12 Votes
Login to vote

Hi All,

Check out the following link to know about how to Migrate an existing Wise Package Studio Server to a new server.

http://www.linkedin.com/groupAnswers?viewQuestionAndAnswers=&discussionID=11593593&gid=56031&trk=EML_anet_qa_ttle-d7hOon0JumNFomgJt7dBpSBA

Please note: You will need to sign in to Linked in to view this article. If you aren't a member of Linked in you will need to signup (it's free).

Thanks,
Arun

Comments 2 CommentsJump to latest comment

Sushma's picture

Do I have to be a member of LinkedIn.com in order to view the discussion?

Can you post the solution for us here?

+2
Login to vote
CableGuy41's picture

Oops, I almost forgot to mention that you need to be a member to view the discussion.
Anyway, i'm pasting the ifnormation for ya:

--------------------------------------------------------------------------
Question:
Reinstalled Wise Package Studio on new server. How do I migrate all our projects to the new Wise Share Point? Is this documented somewhere?
--------------------------------------------------------------------------
Solution:
Our original setup was 1 Wise server and 1 SQL server.
New server was built.

I installed Wise on the new server and pointed it to the same database location on the SQL server as the original installation. At this point is was like any new installation

Once I verified it was working I copied over the wamdb.idx file from the original
Wise Share Point to the new one and it replicated everything.

I also copied over the Componentrules.ini and Repackage.ini since we had already customized them.

I then reinstalled my Wise client on my VM pointing to the new Wise Share Point and edited a package and saved it and all the paths were updated, etc.