Guys

I am doing the backups for my servers. I run the full backup  and when i run the incremental it brings this error Completed status: Completed with exceptions See exception(s)

Completed status: Completed with exceptions See exception(s)
Expand AllCollapse All
Job Information
Job server:SERVER1
Job name:SRVR1 Backup 00027-Incremental
Job started: Sunday, December 29, 2013 at 6:00:04 PM
Job type: Backup
Job Log: BEX_SERVER1_01903.xml

The backup options or selections for this job have changed since the last time it ran. You should run the full backup instance of this backup definition as soon as possible to ensure complete protection. Checkpoint restart cannot be applied to the following resource(s): \\SRVR1\System?StateBackup Exec will not follow mount points, junction points, and symbolic links when the Simplified Disaster Recovery indicator is ON. Drive and media mount requested: 12/29/2013 6:00:06 PM No appendable media could be mounted. Switching to overwrite operation on scratch media.

 

Operating Systems:

Comments 1 CommentJump to latest comment

Jaydeep S's picture

Did anything change in the selection list? Could you try to recreate the job and see if that helps.