Creating a Maintenance Window

Created: 20 Nov 2012 | 2 comments

Hello,

We are running 7.1 and our company has some pretty specific maintenance windows.  I understand how to create a window, however I connot figure out how to align it to these times.

For instance, 7.1 can implement 2nd week Tuesday of each month, but that can differ from Second Tuesday of each month.

Thoughts?

2nd Tuesday of each month (10.00am – 2.00pm) OR  4th Tuesday of each month (11.00pm – 5.00am the following day)

Thank you!

Comments 2 CommentsJump to latest comment

SaschaH's picture

2nd week Tuesday should end up as second Tuesday of a month. It starts counting the weeks with a Tuesday in it. You can test it with a policy schedule if you like. They have the same confusing naming, where as shared schedules are named correctly.

Bechtle – your strong IT partner. Today and tomorrow

If that seems to help, please "Mark as Solution"

Erik864's picture

Thank you for the explanation!

I appreciate your time.