Hello everyone,
I'm planing to upgrade my SEPM 11.0.6 to 12.x (12.1 i think).
I was wondering if any of you already made it and how did you proceed :
I had few thoughts but not sure of wich would be the best (well the more appropriate ...)
I ve about 200 clients, 1 SEPM and 6 differents locations (1 is ou main LAN, 5 others are WAN linked connections)
The SEPM is on an ESX, so i can back it up easily
I was thinking of 3 things :
- Backup everything and upgrade from scratch (i mean launch the installer and let it do what he needs to)
- Using a fresh new install of Windows, installing the 12.x and adding it into the existing (this is where i don t know if the 11.x install will accept a 12.x partner ...) and moving clients to the new server
- Using a fresh install, put the 12.x and smoothly migration of the clients to the new server (via sylink.xml)
First means a downtime of the server
Second i m not sure of it would be doable
Third easy one but means a little more time to move all the clients ...
Thanks for the Help !