  • 1.  Package server problem in altiris

    Posted Sep 20, 2013 03:05 AM

    Hi,

    I have configured package server at remote site since last month and from first week to till date show only 200 packages, even total number of packages are 5000. i had copied whole 'Package Delivery'folder from up to date Package Server and pasted before a week but it still shows only 200 packages.

    what is the reason?



  • 2.  RE: Package server problem in altiris

    Posted Nov 11, 2013 10:24 AM


  • 3.  RE: Package server problem in altiris
    Best Answer

    Posted Nov 25, 2013 07:31 AM

    Ok try below solution,

    Do Check Mark on Created package server which having package transfer prob from Settings-Software-Patch Management-Windows-Patch Remediation Settings  Package server Tab.

    Start Synchronisation with Package Server.

     

    NS Server will transfer all packages to Package Servers.