Endpoint Encryption

 View Only
  • 1.  Schedule unmount of PGP disk

    Posted Feb 22, 2013 10:29 PM

    I'd like to schedule for a pgp virtual drive to automatically unmount at a given time each day if it's mounted. Unfortunately I have no idea how to begin. Suggestions? It's okay for the unmount to fail if files in the virtual drive are open or locked but I'd like something in place to automatically unmount it at a given time each day if possible. My motivation is that I've observed that backups of the pgp file fail if the drive is open at the time the backup is run so I'd like to have something in place to close the drive each day before the backup process runs.

    Thanks!



  • 2.  RE: Schedule unmount of PGP disk

    Posted Feb 22, 2013 11:10 PM

    I'm not into script writing, but suspect it can be done, with using the Windows Task Scheduler to run it at the desired time.  The default hot key is Ctrl+Shift+U. The hot key must be enabled first on the Advanced tab of PGP Options .