Slow Backup with 2 Drives and 2 Jobs
Updated: 21 May 2010 | 5 comments
We have a Dell PowerVault ML6010 with 2 x LTO4 Drives.
Both are using the same firmware and the same symantec tape drive drivers.
We have 2 jobs setup to backup data from the same location but different folders. Both the jobs are backing up about 500GB each. They start at 3AM.
When we first installed the 2nd tape drive and setup the jobs they both finished within 5hrs both with job rates of around 3.5gb/min each. Now for some reason the first job runs at 3.5gb/min and completes within 5hrs but the 2nd job now goes much slower at about 1gb/min and takes 8hrs to complete.
Any help much appreciated.
Discussion Filed Under:
Comments
Marcrp - have you tried testing these jobs as both backup-to-disc. I had this exact same issue and at first put it down to the SCSI card, tried all sorts to resolve it.
Eventually ran both backups as B2D (as well as a combiniation of B2D and to tape) and the issue was still there; whichever backup I started second would kill the speed of the first job.
I ended up running one drive off the backup server and attached the 2nd drive to another server I had available. Obviously, you need a 2nd server, SCSI card and licence - so not an ideal solution.
I was running BE 10d on a PowerEdge 860 using a PowerVault 114T with two LTO3 drives.
See my thread here: https://forums.symantec.com/syment/board/message?b...
Hope this helps you get further than I did!
Would you like to reply?