    Hello,

    • Is it possible to create a new sub-task for an incident once the main task has been resolved?
    • If a sub-task is assigned to a group, can a member of that group reassign the sub-task to another assignee?

    It does not look like the console gives you that cabability, so I am wondering if either of those actions can be done.

    Than you in advance.



  • 2.  RE: Two sub-tasks questions for SD
    Best Answer

    Posted Mar 15, 2012 11:07 AM

    I don't think the first one is possible but the second may be.. In the SD.IncidentManagement project -> Initial Diagnosis model -> Initial Diagnosis Workflow Dialog component -> Interaction Setup tab -> Reassign Incident. If you edit that model and go to the Conditional Use Model you'll see that there is logic there to not display the link if it's a subtask.

    If you make it show the Reassign Incident link then you can probably reassign the subtask to another person/group but I haven't tested it out to see if it does.



  • 3.  RE: Two sub-tasks questions for SD

    Posted Mar 20, 2012 11:09 AM

    Thanks for confirming question number 1.

    I actually see there is a link to reassign sub-task.

    Thanks for the help!